Featured Project

Arlington Wastewater Treatment Plant Upgrade and Expansion, Phase 1

Project Dates: 3/16/2009 - April 2011
Project Location: Arlington, WA
Assistant Project Manager: CJ Handsforth
Owner: City of Arlington- Public Works Department, James Kelly

Award Amount: $26,914,031.33 (pre-tax)
Project Manager: Todd Pike
Superintendent: Kelly Brown
Engineer: Kennedy/Jenks Consultants, Inc., Chris Kelsey

Project Description:

  • Extensive improvements and upgrades include: relocation of utilities, new electrical, natural gas, and water services, demolition of existing building and structures; construction of access roads; walkways, and retaining walls, expansion of the existing headwork structure.
  • This project has strict milestone completion dates for the MBR completion, the Aeration Basin, and Substantial Completion.
  • Keeping the existing plant on line while constructing the new plant and changing process equipment has been very challenging.
  • 5000 CY of Concrete.
  • Coordination and extensive modification, construction and installation of a $6 million Treatment Equipment Package.
  • 2-year project with two intermediate milestones.