Port of Seattle Terminals
25/30 SSAT /Matson
Improvements
Project Description:
This was a fast track project with IMCO crews
working 16-24 hours per day for 100 days
straight.
The job value went from approximately $6 million
to $10 million in added work and quantities
with a fixed job duration.
IMCO’s GPS equipment was critical to the timely
completion and the overall finish product quality
of the Port of Seattle’s newest container storage
yard.
2400 L F of crane foundation and
rail, 1200 L F of new crane electrical
trench, 3 new sewage lift stations,
a new wash rack, 320 container
refrigeration outlets, 2 electrical
substations, utility repairs, asphalt
overlay, new fencing and gates,
striping, wheel stops and signage.