Corporate Headquarters
2116 Buchanan Loop
Ferndale, WA 98248
Phone: (360) 671-3936
Fax: (360) 671-8808
WA License No. IMCOGI*215R1

Featured Project

Hawks Prairie Reclaimed Water Satellite, Wetland Ponds/Recharge Basins-Phase 1

Location: Lacey, WA
Owner: LOTT Wastewater Alliance, Michelle Barnett
Contract Amount: $6,072,598.00 (w/o tax)

Engineer: Brown & Caldwell & Kim Murillo
Project Date: June 12, 2004 - October 6, 2006

Project Description:
The LOTT Alliance is the regional wastewater treatment system serving the cities of Lacey, Olympia, Tumwater and northern Thurston County (LOTT) in Washington State. The core of LOTT's long-range wastewater resource management plan is production of Class A Reclaimed Water, which is the highest quality of reclaimed water as designated by the Washington Departments of Health and Ecology.

  • The project had 600,000 BF of Timber that was logged. Property was then stumped, piled, and chipped.
  • 11.5 acres of wetland ponds were constructed and lined with clay (then topsoil) and had a series of HDPE header pipes installed in them to control levels. The water that fed the ponds was reclaimed water from their treatment plant thru a 14” diameter pipe line.
  • Construction of 8 acres of recharge basins also included installation of large 24” HDPE header piping, which were fed from a series of vaults and used to control the pond elevation.

Points of Interest:

  • All 35 acres (including ponds)were planted with water lilys, and under water vegetation.
  • Walking paths & kiosks for the public to view the site were also constructed.
  • The ponds and recharge basins had to be completed before the completion of the treatment plant, in order to discharge water.
  • Project was completed ahead of schedule.